PMP Certification12 min

Earned Value Management (EVM) for PMP: Formulas, Examples & Exam Tricks

By SkillJet Editorial Team · July 21, 2026

Earned Value Management (EVM) integrates scope, schedule and cost into one performance picture. It is the single most formula-dense area of the PMP exam — and the easiest to score full marks on once the three base values are clear.

The Three Base Values

  • Planned Value (PV): the budgeted cost of work scheduled to be done by now.
  • Earned Value (EV): the budgeted cost of work actually completed by now. EV = % complete × BAC.
  • Actual Cost (AC): the actual money spent for the work done by now.
  • BAC: Budget at Completion — total planned budget.

Everything else derives from these.

Variances (Absolute)

  • Cost Variance: CV = EV − AC
    • CV > 0: under budget. CV < 0: over budget.
  • Schedule Variance: SV = EV − PV
    • SV > 0: ahead of schedule. SV < 0: behind schedule.

Performance Indices (Ratios)

  • Cost Performance Index: CPI = EV / AC
    • CPI > 1: under budget (good). CPI < 1: over budget.
  • Schedule Performance Index: SPI = EV / PV
    • SPI > 1: ahead of schedule. SPI < 1: behind.

Forecasting Formulas

  • EAC (Estimate at Completion): projected total cost at completion.
  • ETC (Estimate to Complete): ETC = EAC − AC.
  • VAC (Variance at Completion): VAC = BAC − EAC.
  • TCPI (To-Complete Performance Index): the efficiency needed to meet BAC: TCPI = (BAC − EV) / (BAC − AC).

Four EAC Formulas — Know When to Use Each

SituationEAC formula
Current variances are atypical (won’t continue)EAC = AC + (BAC − EV)
Current rate will continueEAC = BAC / CPI
Schedule and cost both matterEAC = AC + [(BAC − EV) / (CPI × SPI)]
Initial estimates were flawed, re-estimateEAC = AC + bottom-up ETC

Worked Example

A project has BAC = 200,000. At a status date, 50% of the work is complete (EV = 100,000). PV was 120,000 and AC is 110,000.

  • CV = 100,000 − 110,000 = −10,000 (over budget)
  • SV = 100,000 − 120,000 = −20,000 (behind schedule)
  • CPI = 100,000/110,000 = 0.91
  • SPI = 100,000/120,000 = 0.83
  • EAC (variances continue) = 200,000 / 0.91 = 219,780
  • EAC (variances atypical) = 110,000 + (200,000 − 100,000) = 210,000
  • VAC = 200,000 − 219,780 = −19,780 (over budget at completion)
  • TCPI (to meet BAC) = (200,000 − 100,000)/(200,000 − 110,000) = 1.11 — you must improve to 111% efficiency.

How to Interpret Numbers Fast

  • Negative variance = bad; positive = good.
  • Index < 1 = bad; > 1 = good.
  • EAC > BAC means the project will overrun; VAC is negative.

PMP Exam Tricks

  • The question usually gives you three of PV/EV/AC and asks for a derived value. Write the base values first, then the formula.
  • If the question says “current trend will continue,” use EAC = BAC/CPI.
  • If it says “the remaining work will be done at the budgeted rate,” use EAC = AC + (BAC − EV).
  • TCPI based on BAC tells you the efficiency to finish at the original budget; TCPI based on EAC the efficiency to finish at the revised forecast.

Common Mistakes

  • Mixing EV and AC (EV is budgeted; AC is actual).
  • Using AC instead of EV in the numerator of CPI.
  • Forgetting that ETC = EAC − AC.
  • Choosing the wrong EAC formula for the scenario described.

Memorise the three base values, the four EAC scenarios, and the “negative = bad, < 1 = bad” rule, and EVM becomes guaranteed points on the PMP exam.

Test your knowledge — 10 free PMP questions

See how ready you are. Take a quick 10-question sample quiz — no sign-up required.

Start Free Quiz

Frequently Asked Questions

What is the difference between CV and CPI?

Cost Variance (CV = EV − AC) is the absolute cost difference in money. Cost Performance Index (CPI = EV/AC) is the cost efficiency as a ratio. Both tell you if you are under or over budget, CPI in a normalised way.

How is EAC calculated when past performance is not expected to continue?

Use EAC = AC + (BAC − EV). This assumes the remaining work will be done at the original budgeted rate, ignoring the cost overrun so far.

What does an SPI of 0.8 mean?

The project is progressing at 80% of the planned rate — it is behind schedule. An SPI of 1.0 means on schedule; above 1.0 means ahead of schedule.

Free Audio Mode Included

Get the Free PMP Formulas Cheat Sheet

Enter your email and we’ll send you a one-page PMP formulas + mindset cheat sheet plus free practice scenarios.

No spam. Unsubscribe anytime. We’ll also send you free practice tips.

Skilljet.co

© 2026 Skilljet.co — PMP & Scrum Master exam prep.

Disclaimer: Skilljet.co is an independent exam-preparation platform and is not affiliated with, endorsed by, or sponsored by PMI, Scrum.org, Scrum Alliance, ASME, API, AWS, NEBOSH, OSHA, Saudi Aramco, ADNOC, or any other official certification body. Our practice tests, study guides, and tools are intended solely for preparation and self-assessment. Completing our courses or passing our mock exams does not grant, award, or guarantee any official, accredited, or recognized certification. To obtain a valid certification, you must register with and pass the official exam administered by the respective governing body.