How it works
Edit the activity network, then run a forward/backward pass to compute ES, EF, LS, LF and float. The critical path (zero-float) is highlighted. Apply crashing (shorten durations at a cost) or fast-tracking (parallelize dependencies) to compress the schedule per PMBOK 7.
Compression Mode:
| ID | Activity | Dur (d) | Preds | ES | EF | LS | LF | Float |
|---|---|---|---|---|---|---|---|---|
| A | Mobilize | — | 0 | 5 | 0 | 5 | 0 | |
| B | Excavate | A | 5 | 15 | 5 | 15 | 0 | |
| C | Foundation | B | 15 | 27 | 15 | 27 | 0 | |
| D | Structure | C | 27 | 47 | 27 | 47 | 0 | |
| E | MEP Rough-in | D | 47 | 62 | 50 | 65 | 3 | |
| F | Finishes | D | 47 | 65 | 47 | 65 | 0 | |
| G | Commissioning | E,F | 65 | 72 | 65 | 72 | 0 | |
| H | Handover | G | 72 | 75 | 72 | 75 | 0 |
Critical Path
H → G → F → D → C → B → A
Project Duration
75 days
Crash Cost
$0