Transitioning from Waterfall to Agile in a Hybrid Project
Scenario
Your organization has traditionally used a predictive (waterfall) approach. A new executive wants to transition the current project to Agile, but the team has no Agile experience and the project is already 40% complete. The customer is concerned about the transition. What should the project manager do?