Critical Path Method and Schedule Compression Techniques for PMP
Scenario
Your construction project has a planned duration of 18 months. After a 3-week delay in the foundation phase, the sponsor demands the original completion date be preserved. The critical path runs through foundation → structure → MEP → finishing. You have $200,000 in management reserve. What schedule compression technique should you evaluate first, and what are the trade-offs?