Choosing the Right Contract Type: PMP Procurement Decision Scenarios
Scenario
You are procuring a custom software development vendor for a 10-month project. The requirements are 70% defined but 30% is expected to evolve based on user testing. The vendor proposes three options: (A) Firm Fixed Price (FFP) at $500,000, (B) Cost Plus Fixed Fee (CPFF) at estimated $480,000 + $50,000 fee, or (C) Time & Materials (T&M) at $150/hour. The sponsor wants cost certainty. The team wants flexibility. Which contract type should you recommend and why?
Frequently Asked Questions
Ready for the full PMP exam experience?
Take our free PMP diagnostic with 180 exam-style questions.
Take Free PMP Diagnostic