Choosing the Right Contract Type: PMP Procurement Decision Scenarios

Scenario

You are procuring a custom software development vendor for a 10-month project. The requirements are 70% defined but 30% is expected to evolve based on user testing. The vendor proposes three options: (A) Firm Fixed Price (FFP) at $500,000, (B) Cost Plus Fixed Fee (CPFF) at estimated $480,000 + $50,000 fee, or (C) Time & Materials (T&M) at $150/hour. The sponsor wants cost certainty. The team wants flexibility. Which contract type should you recommend and why?