pert · Engineering Calculator

PERT Calculator for Construction Project Duration (3-Point Estimate)

Formula

Expected Time = (Optimistic + 4×Most Likely + Pessimistic) / 6

Governing Standard

PMI PMBOK Guide, PERT technique

Required Inputs

  • Optimistic estimate O (days)
  • Most likely estimate M (days)
  • Pessimistic estimate P (days)

Output

Expected duration (days) and standard deviation

Notes

The PERT formula gives a weighted average that accounts for uncertainty. The standard deviation is (P-O)/6, which helps calculate confidence intervals. For a 90% confidence level, add 1.3× standard deviation to the expected time.