PERT Three-Point Estimate Calculator for Construction Activity Duration

Formula

te = (O + 4M + P) / 6; SD = (P - O) / 6; Variance = SD²

Governing Standard

PMI PMBOK 7th Edition — Schedule Management, and PERT (Program Evaluation Review Technique)

Required Inputs

  • Optimistic Estimate (O) in days
  • Most Likely Estimate (M) in days
  • Pessimistic Estimate (P) in days

Output

Expected Duration (te), Standard Deviation (SD), 68% Range, and 95% Range in days

Notes

For an activity with O=10, M=14, P=26 days: te = (10 + 56 + 26)/6 = 15.3 days. SD = (26-10)/6 = 2.67 days. 68% confidence range: 12.6 to 18.0 days. 95% confidence range: 10.0 to 20.6 days. The PERT formula weights the most likely estimate 4x more than optimistic or pessimistic, reflecting the beta distribution assumption.