Procurement Management for PMP

Procurement management covers acquiring goods and services from external sources. It's a tested topic in the Process domain — especially contract types and risk allocation. This guide breaks it down.

The Procurement Management Process

  1. Plan Procurement Management — decide what to buy and how
  2. Conduct Procurements — select sellers and award contracts
  3. Control Procurements — manage seller performance

Make-or-Buy Analysis

Before procuring, decide whether to make or buy:

  • Make: Core capability, strategic control, cost-effective at scale
  • Buy: Specialized expertise, faster, lower upfront investment

Contract Types

Fixed-Price Contracts

Seller agrees to deliver for a fixed price. Risk on seller.

TypeDescription
Firm Fixed Price (FFP)Fixed price, no adjustment
Fixed Price Incentive Fee (FPIF)Fixed price plus incentive for performance
Fixed Price with Economic Price Adjustment (FPEPA)Adjusts for inflation over long contracts

When to use: Well-defined scope, buyer wants cost certainty.

Cost-Reimbursable Contracts

Buyer reimburses seller's actual costs plus a fee. Risk on buyer.

TypeDescription
Cost Plus Fixed Fee (CPFF)Reimburse costs plus fixed fee
Cost Plus Incentive Fee (CPIF)Reimburse costs plus incentive based on performance
Cost Plus Award Fee (CPAF)Reimburse costs plus subjective award fee

When to use: Uncertain scope, research work, flexibility needed.

Time and Material (T&M)

Hybrid — hourly rate with a ceiling. Risk shifts based on usage.

When to use: Small scope, uncertain duration, staff augmentation.

Risk Allocation

Contract TypeRisk on BuyerRisk on Seller
Fixed-priceLowHigh
Cost-reimbursableHighLow
T&MMediumMedium

Procurement Documents

  • Request for Information (RFI): Seek information, no commitment
  • Request for Proposal (RFP): Seek detailed proposals — used for complex procurement
  • Request for Quotation (RFQ): Seek price quotes — used for commodity procurement

Source Selection Criteria

Buyers evaluate sellers on:

  • Technical capability
  • Cost
  • Schedule
  • Past performance
  • References
  • Financial stability
  • Approach and methodology

Conducting Procurements

  1. Issue RFP/RFQ to qualified sellers
  2. Receive proposals
  3. Evaluate against source selection criteria
  4. Select seller (often via weighted scoring)
  5. Award contract

Controlling Procurements

  • Monitor seller performance against contract terms
  • Manage changes through change control
  • Inspect deliverables before acceptance
  • Close out contracts formally (administrative and financial closure)

The PMI Mindset for Procurement

  1. Define scope clearly — vague scope leads to disputes
  2. Choose contract type based on risk — match to situation
  3. Document everything — contracts, changes, performance
  4. Inspect before accepting — verification is the buyer's responsibility
  5. Close contracts formally — don't leave loose ends

Common Procurement Exam Traps

  • Picking fixed-price when scope is uncertain (should be cost-reimbursable)
  • Forgetting that cost-reimbursable puts risk on the buyer
  • Confusing RFI (information) with RFP (proposal) with RFQ (quote)
  • Missing that T&M needs a "not-to-exceed" ceiling to limit buyer risk

Final Thoughts

Procurement rewards clear thinking about risk allocation: fixed-price shifts risk to the seller, cost-reimbursable keeps it on the buyer, T&M splits it. Match the contract type to the scenario's risk profile, and you'll handle procurement questions with confidence.

Test your knowledge — 10 free PMP questions

See how ready you are. Take a quick 10-question sample quiz — no sign-up required.

Start Free Quiz

Frequently Asked Questions

What are the three main contract types in PMP?

Fixed-price (firm fixed price, FPIF, FPEPA), Cost-reimbursable (CPFF, CPIF, CPAF), and Time and Material (T&M). Each allocates risk differently between buyer and seller.

Which contract type puts the most risk on the seller?

Fixed-price contracts put the most risk on the seller — they must deliver for the agreed price regardless of actual costs.

When should a buyer use a T&M contract?

T&M contracts suit small, uncertain-scope work where neither fixed-price nor cost-reimbursable fits — often used for staff augmentation or short expert engagements.

Free Audio Mode Included

Get the Free PMP Formulas Cheat Sheet

Enter your email and we’ll send you a one-page PMP formulas + mindset cheat sheet plus free practice scenarios.

No spam. Unsubscribe anytime. We’ll also send you free practice tips.

Skilljet.co

© 2026 Skilljet.co — PMP & Scrum Master exam prep.

Disclaimer: Skilljet.co is an independent exam-preparation platform and is not affiliated with, endorsed by, or sponsored by PMI, Scrum.org, Scrum Alliance, ASME, API, AWS, NEBOSH, OSHA, Saudi Aramco, ADNOC, or any other official certification body. Our practice tests, study guides, and tools are intended solely for preparation and self-assessment. Completing our courses or passing our mock exams does not grant, award, or guarantee any official, accredited, or recognized certification. To obtain a valid certification, you must register with and pass the official exam administered by the respective governing body.