Crane Lifting Plan Design: A Complete Guide to BS 7121 & LOLER Compliance
By SkillJet Editorial Team · August 22, 2026
Crane Lifting Plan Design: A Complete Guide
A crane lifting plan is a documented procedure that ensures every lift is carried out safely. Under BS 7121 (British Standard for crane safe use) and the Lifting Operations and Lifting Equipment Regulations 1998 (LOLER), every lifting operation must be properly planned by a competent person — the Appointed Person (AP). This guide covers the essential calculations and documentation for a compliant lifting plan.
The Role of the Appointed Person
The Appointed Person (AP) is the competent individual responsible for:
- Planning the lifting operation
- Selecting appropriate lifting equipment and accessories
- Assessing ground conditions and environmental factors
- Producing the lifting plan and risk assessment
- Briefing the lifting team
The AP does not necessarily operate the crane but holds overall responsibility for the lift's safety.
Key Lifting Plan Calculations
1. Total Gross Load
The total load the crane must lift includes not just the payload but all rigging:
Total Gross Load = Payload + Rigging Weight + Hook Block Weight + Dynamic Allowance
Dynamic allowance accounts for wind, crane movement, and sudden stops — typically 10% for standard lifts, 25% for rapid or multi-crane lifts.
Example: Lifting a 5-tonne steel beam with 0.5-tonne rigging and 0.3-tonne hook block:
Total Gross Load = 5.0 + 0.5 + 0.3 + (5.0 × 10%) = 6.3 tonnes
2. Crane Utilization (Capacity Ratio)
Crane utilization tells you how much of the crane's rated capacity you're using:
Utilization (%) = (Total Gross Load / Crane Rated Capacity at Radius) × 100
Industry best practice:
- < 75%: Green — safe, normal lift
- 75–85%: Amber — caution, requires additional controls
- > 85%: Red — critical lift, requires enhanced planning and permits
3. Working Radius
The working radius is the horizontal distance from the crane's center of rotation (slew center) to the hook:
Radius = Horizontal distance from slew center to load CG
Crane capacity charts show the rated capacity at each radius and boom length. Always verify the crane can lift the gross load at the maximum radius during the lift cycle — not just at the pick point.
4. Sling Tension Calculation
For a two-leg sling at an angle θ from vertical:
Tension per leg = (Total Load / 2) / cos(θ)
| Sling Angle (from vertical) | Tension Factor | Load Multiplier |
|---|---|---|
| 0° (vertical) | 1.000 | 1.00× |
| 30° | 1.155 | 1.15× |
| 45° | 1.414 | 1.41× |
| 60° | 2.000 | 2.00× |
Example: 10-tonne load on a 2-leg sling at 45°:
Tension per leg = (10 / 2) / cos(45°) = 5 / 0.707 = 7.07 tonnes per leg
Critical: Never exceed 60° sling angle (from vertical) — tension doubles and sling WLL is effectively halved. BS 7121 recommends keeping sling angles at 60° or less from horizontal (30° from vertical).
5. Outrigger Mat Sizing
Outriggers transfer the crane's load (including the lifted load) to the ground. The mat must spread the load over enough area to prevent ground failure.
Required Mat Area = Outrigger Reaction Force / Allowable Ground Bearing Pressure
Outrigger reaction force can be up to 75% of the total gross load + crane weight on the most heavily loaded outrigger during a side lift.
Example: 40-tonne outrigger reaction on firm ground (200 kN/m²):
Required Area = (40 × 9.81) / 200 = 1.96 m²
A 1.4 m × 1.4 m timber mat (1.96 m²) would be required.
Ground Condition Assessment
Ground bearing capacity is critical. Common values:
| Ground Type | Bearing Capacity (kN/m²) |
|---|---|
| Soft clay | 50–100 |
| Firm clay | 100–200 |
| Loose sand | 100–200 |
| Dense sand/gravel | 200–400 |
| Weak rock | 500–1,000 |
| Concrete (C25) | 5,000+ |
Always conduct a ground bearing assessment or geotechnical report before heavy lifts. Use steel or timber mats, crane pads, or road plates to distribute load.
Environmental Factors
Wind Speed Limits
Most crane manufacturers specify a maximum wind speed for lifting — typically 9–11 m/s (20–25 mph) for general lifts. For tower cranes and high-boom lifts, the limit may be lower.
Wind force on the load increases with the square of wind speed and with the load's exposed area. Large, flat loads (sail effect) require lower wind limits.
Temperature and Visibility
- Extreme cold affects crane hydraulics and steel toughness
- Rain/snow reduces ground bearing capacity
- Poor visibility requires additional lighting or lift postponement
Lifting Plan Documentation
A compliant lifting plan (per BS 7121) must include:
- Project details — site, date, lift number
- Load details — weight, dimensions, CG, lifting points
- Crane details — type, capacity chart, configuration
- Rigging details — sling type, WLL, angles, accessories
- Ground conditions — bearing capacity, matting plan
- Environmental limits — wind speed, visibility
- Method statement — step-by-step lift sequence
- Risk assessment — hazards and controls
- Sign-off roster — AP, crane operator, slinger/signaller, banksman
- Verification — QR code linking to digital verification
LOLER Examination Requirements
LOLER requires thorough examination of lifting equipment:
- Before first use (unless accompanied by valid examination certificate)
- Every 6 months for equipment used to lift persons
- Every 12 months for other lifting equipment
- After exceptional circumstances (damage, long idle periods)
Examination must be by a competent person and results recorded in the Register of Lifting Equipment.
Tools for Lifting Plan Design
The SkillJet Crane Lifting Plan Calculator automates load calculations, crane utilization, sling tension, and outrigger mat sizing. It generates a 3-page PDF engineering package with load breakdowns, 2D geometry sketches, and authorization rosters — all with QR verification.
Conclusion
A well-designed crane lifting plan protects workers, the public, and the load. By mastering gross load calculation, crane utilization, sling tension, and outrigger mat sizing — and documenting everything per BS 7121 and LOLER — the Appointed Person ensures every lift is executed safely. Never compromise on planning; a 10-minute calculation can prevent a lifetime of consequences.
Frequently Asked Questions
What is the role of the Appointed Person in a crane lift?
The Appointed Person (AP) is the competent individual responsible for planning the lifting operation, selecting equipment, assessing ground and environmental conditions, producing the lifting plan and risk assessment, and briefing the lifting team. The AP holds overall responsibility for lift safety under BS 7121 and LOLER.
What is the maximum safe crane utilization percentage?
Industry best practice recommends keeping crane utilization below 75% for normal lifts (green), 75–85% requires additional controls (amber), and above 85% is a critical lift requiring enhanced planning and permits (red).
How is sling tension calculated for an angled sling?
Tension per leg equals the total load divided by the number of legs, divided by the cosine of the sling angle from vertical. At 45° from vertical, tension is 1.41× the load share; at 60°, it doubles. Never exceed 60° from vertical.
How often must lifting equipment be examined under LOLER?
LOLER requires thorough examination before first use, every 6 months for equipment lifting persons, every 12 months for other lifting equipment, and after exceptional circumstances like damage or long idle periods.
Stop Memorizing. Start Training Your PMI Mindset.
Practice scenario questions hands-free with Audio Mode and track your domain readiness before paying exam fees.
Start Free PMP Practice